Wednesday, September 21, 2016

Bad Trends and Sloppy Velocity

Read this: https://www.linkedin.com/pulse/story-points-evil-brad-black-in-the-market-

There are good quotes from Ron Jeffries on the worthlessness of story points. (I've heard this from other Agile Consultants, also.) Story Points are a political hack to make management stop measuring the future.

The future is very hard to measure. The difficulty in making predictions is one of the things which distinguishes the future from the past. There's entropy, and laws of thermodynamics, and random quantum events that make it hard to determine exactly what might happen next.

If Schrödinger's cat is alive, we'll deliver this feature in this sprint. If the cat is dead, the feature will be delayed. The unit test result is entangled with the photon that may (or may not) have killed the cat. If you check the unit tests, then the future is determined. If you don't check the unit test, the future can be in any state.

When project management becomes Velocity Dashboard Centered (VDC™), that's a hint that something may be wrong.

My suspicion on the cause of VDC?

Product Owners ("Management") may have given up on Agility, and want to make commitments to a a schedule they made up on a whiteboard at an off-site meeting. Serious Commitments. The commitment has taken on a life of its own, and deliverable features aren't really being prioritized. The cadence or tempo has overtaken the actual deliverable.

It feels like the planning has slipped away from story-by-story details.

What can cause VDC?

I think it might be too many layers of management. The PO's boss (or boss's boss) has started dictating some kind of delivery schedule that is uncoupled from reality. The various bosses up in the stratosphere are making writing checks their teams can't cash.

What can we do?

I don't know. It's hard to provide schooling up the food chain to the boss of the boss of the product owner. It's hard to explain to the scrum master that the story points don't much matter, since the stories exist independent of any numbering scheme.

The link above says that there's some value in ordering the stories; assigning random-ish point numbers somehow helps order them.

I reject the last part of this. The stories can be ordered without any numbers. The Agile manifesto is pretty clear on this point: talk about it. The points don't enhance the conversation. Push the story cards around on the board until you have something meaningful. Assigning numbers is silliness.

Actually. I think its harmful.

Rolling numbers up to "senior" management isn't facilitating a conversation. It's summarizing things with empty numerosity. ("Numerosity"? Yes. Empty numerosity: applying numeric methods inappropriately. For example, averaging the day of the week on which it rains, for example, to discover something about Wednesday.)

The Best Part (TBP™)

Irreproducibility.

On Project X, we had a velocity of 50 Story Points per Sprint. On Project U, the "same" team -- someone quit and two new people were hired -- had a velocity of 100 Story Points per Sprint. Wow! Right?

Except. Of course, the numbers were inflated because the existing folks figured the new folks would take longer to get things done. But the new folks didn't take longer. And now the team is stuck calling a 3-point story a 5-point story because the new guys are calibrated to that new range of random numbers.

So what's comparable between the "same" team on two projects? It's not actually the same people. That's out.

We can try to pretend that the projects have the "same" technology (Java 1.6 v. Java 1.8) or the same CI/CD pipeline (Ant v. Maven, Hudson v. Jenkins) or even the same overall enterprise. But practically, there's nothing repeatable about any of it. It's just empty numerosity.

Sorry. I'm not sold, yet, on the value of Story Points.

Tuesday, May 5, 2015

Scrum, Agile, and Modern Tools

Required Reading: https://www.pandastrike.com/posts/20150304-agile

My takeaway quote? "Scrum lags behind the modern toolchain enough that there can be a Potemkin village vibe to the whole thing."

I was clued into this from another takeaway quote someone seconded on Twitter: "Waterfall used too much written communication, but Agile doesn't use enough."

Also read this: http://caines.ca/blog/2014/12/02/i-dont-miss-the-sprint/

Is "sprint" misleading? What about "sprint commitment?"

I'm not sure I object to "sprint" per se.

But I have seen "sprint commitment" turned into an organizational problem, removing what could have been a helpful tool. Folks who start harping on sprint commitments in the sense of "we committed to this, will we meet the deadline?" tend to create a toxic environment. I think the people who hype commitment the most really liked the non-Agile environments: they try bend Agile to meet their Waterfall concepts.

The problem is the word. A "sprint commitment" shouldn't be used like a legally binding "do it or pay penalties" commitment. It should be a metric used to gauge progress. More like a "sprint outcome".

The commitment hype can lead to stories, epics and detailed technical tasks getting muddied up terribly. The story becomes an epic. Little tiny technical tasks get inflated into big important stories. A proper user story gets replaced with nonsense about prepping a database for production rollout, or resolving defects found in QA, or things that -- obviously -- aren't user stories, but are taking up a lot of time.

When it appears that a story is going nowhere, the scrum master breaks it down into things that have status which changes frequently. The sense of end-user meaning behind the actual story gets lost in a haze of technical considerations and tasks that show activity more than accomplishment more than value.

"As an actuary, I want to know that the developers have written syntactically correct DML for my database, so that the product owner don't have to wait as long for the DBA's to build the database."

Really?

Thursday, July 25, 2013

Database Conversion or Schema Migration

I was told a horror story about a bad database schema migration. Let's call the author of the horror story HPL.

HPL related a tale of woeful conversion problems from a mismanaged schema migration.

While I could feel HPL's pain, the reasons given for their pain were wrong. They didn't quite get the lessons they had learned. Consequently, HPL sounded like someone doomed to repeat the mistake, or—worse—unlearning their lessons.

Here's HPL's most distressing comment.
"we can't migrate over the weekend and be done w/ it."
Apparently, the horror of a weekend migration was somehow desirable to HPL. Who wants a lost weekend? And who wants to put all of the eggs in a single basket?

Anyone who's done more than one "lost weekend migration"—and who's also honest—knows that they don't go well. There are always subsets of data that (a) don't get converted properly and (b) have to get swept under the carpet in order to claim to meet the schedule.

It's a standard situation to have less than 100% of the data successfully converted and still call the effort a success. If 100% was not required, why lose a weekend over it?

Good Plans and Bad Plans

From far wiser people than me, I learned an important lesson in schema migration.

These Wiser Heads ran a "conversion" business. They moved data and applications from platform to platform. They knew a lot about database schema migrations. A lot.

Their standard plan was to build a schema migration script (usually a sequence of apps) that could be run to convert the database (or files or whatever) from old to new schema as often as was necessary.

I'll repeat that.

As often as was necessary.

They debugged the script to get to an acceptable level of conversion. The data conversion (or schema migration) was perfectly repeatable. Of course, they longed for 100% conversion; but pragmatically, the legacy software had bad data. So some fraction would not convert. And once that fraction was found, the schema migration applications could be modified to treat the non-convertable data in some intelligent way.

Their stated goal was to convert data and run parallel testing with that converted data as often as necessary to create confidence that the new data was as perfect a conversion as was possible. At some point, the confidence became certainty and the parallel testing was deemed complete. Since they were parallel testing with live data, the decision amounted to a formalized "commissioning" of the new application. And by then, the new application was already being used.

There are bad ways to do schema migration, of course. HPL listed many.

Horrible Mistakes

The horror story from HPL included this:
"For the migrated tables, create views in the old system and create instead of triggers on those views to ship data to the new system."
It appears that they used views and triggers to create a new system "facade" over the legacy system. Apparently, they wanted both suites of application software to coexist. Not a good approach to schema migration. It appeared that they were trying to share one database with two application schema.

This seems like it's doomed. Unless they're all geniuses.

Wiser Heads would have strongly suggested that the new system use a extract of the old system's data.

HPL goes on to complain,
"Sometimes we can take over a column or 2 and sometimes we can only take over some of the data in the table".  
HPL emphasizes this point with "This is not that far fetched". I'm not sure why the emphasis was needed.

This is not "far fetched". It doesn't need emphasis. It's not really much of a problem, either. It's a standard part of schema migration. Extracting a copy of the data makes this quite easy. Triggers and views to create some kind of active SQL-based Facade is what created the complexity. Not the number of columns involved.

HPL summarizes,
"So you end up w/ [many] tables/views triggers all moving data back and forth and faking stuff out"
Back and forth. A fundamental mistake. A copy can be much easier to manage. One way data movement: Legacy to New.

HPL concludes with a litany of errors of various types: performance, change management, file system issues, error logging and auditing. Blah blah blah. Yes, it was a nightmare. I feel their pain.

What About Coexistence? 

It appears that HPL was involved in a project where the entire old and new applications were supposed to somehow coexist during the conversion.

It appeared that they failed to do any kind of partitioning.

Coexistence is not a trivial exercise. Nor is it a monolith where the entire legacy application suite must coexist with the entire new schema and the entire new application suite.

Pragmatically, coexistence usually means that some portion of the legacy must be kept running while some other portion is modernized. This means the coexistence requires that the application portfolio be partitioned.

Step 1: Some suite of functionality is migrated. That means data from the legacy database/file system is copied to new. That also means some data from new is copied back into the legacy database file/system. Copied.

Step 2: Some other suite of functionality is migrated. As functionality is moved, less and less data is copied back to the legacy.

At some point, this copying back is of no value and can be discontinued.

What About Timing?

This copying clearly requires some coordination. It's not done haphazardly.

Does it require "real time" data movement? i.e. triggers and views?

Rarely is real time movement required. This is the point behind partitioning wisely. Partitioning includes timing considerations as well as data quality and functionality considerations.

It's remotely possible that timing and partitioning are so pathological that data is required in both legacy and new applications concurrently. This is no reason to throw the baby out with the bathwater. This is nothing more than an indication that the data is being copied back to the legacy application close to real time.

This also means performance must be part of the test plan. As well as error handling and diagnostic logging. None of this is particularly difficult. It simply requires care.

Lessons Learned

HPL appeared to make the claim that schema migration is super hard. Or maybe that coexistence is really hard.

Worse, HPL's horror story may be designed to indicate that a horrifying lost weekend is the only way to do schema migration.

Any or all of these are the wrong lessons to learn.

I think there are several more valuable lessons here.

  1. Schema migration can and should be done incrementally. It's ideally tackled as an Agile project using Scrum techniques. It's okay to have release cycles that are just days apart as each phase of the conversion is run in parallel and tested to the user's satisfaction.
  2. Coexistence requires partitioning to copy any data back to unconverted legacy components. Triggers and views and coexistence of entire suites of software make a difficult problem harder.
  3. The conversion script is just another first-class application. The same quality features apply to the conversion as to every other component of the app suite.
  4. The conversion must be trivially repeatable. It must be the kind of thing that can be run as often as necessary to move legacy data to the new schema. 

Tuesday, August 7, 2012

How Expensive is a "Waterfall" Project Plan?

It's impossible to step into the same river twice; other waters are flowing toward the sea.  It's impossible to do "head-to-head" project comparisons.  You can't have the same people doing the same thing with only one constraint changed.  You can try to resort to having similar people doing the exact same thing.

It's impossible to provide trivial quantification of the costs of a waterfall approach.  However, there's a lot of places where "up front" engineering adds cost and risk.  A waterfall plan adds friction, zero-value administrative costs and (sometimes) extra work.

For software development that doesn't involve "toy" projects, but apply to the magical "real world" projects, it's difficult to justify building the same "real world" thing twice.  It's hard to create a detailed and purely economic analysis of this question.  Therefore, we have to resort to hand-waving and speculation.

[I put "real world" in quotes, because the "real world" is a kind of dog-whistle phrase that only project managers understand.  It appears to mean "projects that fit my preconceived notions" or "projects that can't be done any other way because of political considerations" or "projects constrained by a customer to have a farcical structure".  Another variant on this dog-whistle phrase is "the realities of running a business."  There's something in their real world that they (a) can't define and (b) prevents any change.]

A few months back, I saw a http://prezi.com presentation that was intended to drive architecture, cost and schedule conversations.  The authors were happy.  I was left relatively mystified.

There are three relevant issues that don't fit well into a prezi presentation.
  1. Open Technology questions.  If it's new software development, there are unanswered software API, performance, quality, fitness-for-purpose questions.  If it's a clone or a clean-room reverse engineering, then there may be few questions.  Otherwise, there must be unknowns.
  2. Open User Story questions.  If it's new software development, then the user stories are not complete, consistent and optimized.  There must be something missing or extra.
  3. Open User Experience questions.  I'm not a UX person.  Tinkering with an Arduino has taught me that even in the most prosaic, simplistic project there is a UX element.  
It's easy to trivialize this as "details" or "supporting information" omitted from the presentation.  Actually, it's considerably more interesting that simply elaborating details.  Indeed, the missing stuff is often more important that the elements of the presentation than were provided.

The Standard Gaps

While a presentation can show some elements of UX, it's not interactive.  It cannot provide any useful depth on the UX.  Failure to do UX exploration (with real interaction) is crazy.  Making assumptions about UX is more likely to create cost and risk.

User Stories can be kicked around in a presentation.  However.  Once the highest-priority user stories are built, and lessons learned about the users, the problem and the emerging solution, then the other user stories can (and should) change based on those lessons learned.  Assuming a list of user stories and then committing to a specific schedule enshrines the costs in a bad plan.  And we all know that the plan (and the dates) are sacred once written down.

Software does not exist in a vacuum.

I'll repeat that, since it's a hidden assumption behind the waterfall.


Software does not exist in a vacuum.

You have a Heisenberg problem when you start building software and releasing it incrementally.  The presence of the new software, even in a first-release, beta-test, barely-working mode changes the ecosystem in which the software exists.  Other applications can (and will) be modified to adjust to the new software.  Requirements can (and should) change.

A waterfall project plan exists to prevent and stifle change.  A long list of tasks and dates exists to assure that people perform those tasks on those dates.  This is done irrespective of value created and lessons learned.

Technology changes.  Our understanding of the technology changes.  One wrong assumption about the technology invalidates the deliverables for a sprint.  In a project with multiple people, multiple assumptions and multiple sprints, this effect is cumulative.  Every assumption by every person for every technology is subject to (considerable) error.

Every technology assumption must be looked at as a needless cost that's being built into the project.

Recently, I've been working on a project with folks that don't know Django very well.  Their assumptions are -- sometimes -- alarming.  Part way through a sprint, I got a raft of technical questions on encrypting passwords.  It's hard to state it strongly enough: never encrypt a password.  What's more useful is this: always hash passwords.  The original password must be unrecoverable.  There are lots of clever hashing techniques.  Some of which are already part of Django.  A significant portion of the sprint (appeared) to be based on reinventing a feature already part of Django.

Do the math: a few wrong assumptions made during project planning are canonized forever as requirements in the project.  With a waterfall project, they're not easy to change.  Project managers are punished for changing the project.  You can't increase the project deadline; that's death.  You can't decrease it, either: you get blamed for sand-bagging the estimates.

Arduino Technology Lessons Learned

After buying several 74HC595 shift registers from Sparkfun, I realized that my assumptions about the interfaces were utterly wrong.  I needed to solder a mix of right-angle header and straight-through headers onto the breakout boards.  I tried twice to order the right mix headers.  It seems so simple.  But assumptions about the technology are often wrong.

This is yet more anecdotal evidence that all assumptions must be treated as simple lies.  Some managers like to treat assumptions as  "possibly true" statements; i.e., these are statements that are unlikely to be false.  This is wrong.  Assumptions always have a very high probability of being false, since they're not based on factual knowledge.

Some managers like to treat assumptions as "boundary conditions":  i.e.,  if the assumption is true, then the project will go according to plan.  Since all of the assumptions will be prove to be incorrect, this seems like simple psychosis.  

[Interestingly, the assumptions-are-boundary folks like to play the "real world" card: "In the real world, we need to make assumptions and go forward."  Since all assumptions will be shown to be incorrect, why make them?  Wouldn't it be more rational to say "we need to explore carefully by addressing high-righ unknowns first"?  Wouldn't it be better to both gather facts and build an early release of the software at the same time?]

Arduino User Story Assumptions

After building a prototype that addressed two of the user stories, it slowly became clear that the third user story didn't actually exist.

Sure, the words were there on paper.  Therefore, there's a user story.

But. 

There was nothing to actually do.  

The whole "As a [role], I need [feature] so that I can [benefit]" that was written on day one was based on a failure to understand precisely how much information was trivially available.  The benefit statement was available with a small software change and no separate user story.  And no separate hardware to support that user story.

Exploration and tinkering reduced the scope of the work.  In the real world.

[In the "real world" where waterfall is considered important, exploration is described as unbounded spending of limited resources.  In the real real world, money must be spent; it can either be long hand-wringing meetings or it can be prototype development.]

The user story (written before a prototype existed) was based on a failure to fully understand the UX.  The only way to fully understand the UX is to build it.  Education costs money.

Arduino UX Learnings

Perhaps the most important issue here is UX.

Once upon a time, UX was expensive, difficult and complex.  So difficult that special-purpose prototyping tools were created to make it possible to create a preliminary UX that could be used to confirm UX and user stories.

This UX prototyping effort was real money spent as part of "requirements" or "design"; it created documentation that flowed over the waterfall for subsequent development.

This notion is obsolete.  And has been obsolete for several years.

UX is now so easy to build that it makes much more sense to build two (or three) competing UX's and compare them to see which is actually better.

Indeed, it makes a lot of sense to build one UX and release it; make a real effort at solving the user's problems.  Then build a second UX for A/B testing purposes to see if there's room for improvement.

I'll repeat that for folks who really like the waterfall.

It's now cheaper to actually build two than it is to write detailed requirements for one.

[In the "real world", this is deprecated as "wasting time playing with the UX".  As if written requirements based on nothing more than a whiteboard are more "real" than hands-on experience with the UX.]

You can prove this to yourself by actually observing actual UX developers knocking out pages and screens.  Long "requirements gathering" meetings with prospective users amount to a waste of time and money.  Long "brainstorming" sessions, similarly, are wasteful.  Short, ongoing conversations, a build, a release, and a follow-up review has more value, and costs less.  

Do the math.  Several users and business analysts in several multiple-hour meetings costs how much?

A pair of developers banging out fully-functioning, working UX for a use case costs how much?

A slavish adherence to waterfall development creates "real world" costs.

Tuesday, May 22, 2012

Delusional Project Managers

Maybe it's the circle-R in the PMP® signature that put me off.

What's important is that the PMP-certified project manager is absolutely married to fixed-price software development.  The idea of "Agile" was unthinkable.  They were very clear that we had enough information to create a fixed price.

It's hard to disagree with someone who's sure that their presentation is a pinnacle of project specification.

Slides 2 and 3 are an overview that lists some broad, vague buzzwords.  ("Asset", "Resource")

Slides 4 to 7 are blurry screen shots of the legacy application.  There must be dozens of pages.  We were shown four.

Slide 8 is a list of project objectives with no priorities, actors or user stories.  "Modify tool navigation to be more intuitive and efficient."  That's the kind of stuff that's supposed to define the scope with enough detail to create a fixed price.

Slide 9 is  another list of objectives.  "Create a simple project and resource KPI dashboard showing real-time status."  I'm not even sure we can define a fixed-price task for figuring out what this might mean.

Slide 10 is a schedule in which all of the dates are already in the past.

We were told -- firmly and finally -- that we were supposed to fabricate a fixed price proposal from this PPT.  We were encouraged to ask follow-up questions.

My first follow-up question should be "Are you crazy?"

My second follow-up question should be "How much time are you willing to put into this effort?  If it's less than 4 hours per day, we can't really help much."

I'm guessing that we're just "column fillers".  There's an incumbent team that has an existing proposal to extend or rewrite; we're merely providing an outside, "independent" quote that can be used for comparison purposes.  The incumbent team probably knows (in detail) the actors and user stories, and has a carefully prioritized feature set.  We don't even know (precisely) what's in the data model.

I would like to avoid writing a "column filler" proposal that will be a million dollars more than they had in mind.

An Agile approach (5 people × 8 hrs × 15 days = 600 labor hours per sprint) was refused.

If they would reveal their budget, we could have a more meaningful conversation on what they can get finished and delivered for that little dribble of money.

I think that PMP best practices are getting in the way of a successful software development effort.

Tuesday, January 3, 2012

Epic indictment of Waterfall Methods

Saw this recently.

I think this aptly summarizes the results of a waterfall methodology.
  1. You wrote a lot of requirements, not fully understanding the actors or their use cases.
  2. Your vendor implemented those requirements because they were contractual obligations not because they created value for the actors.
The government's not the only offender.  They're just more visible and more bound up in a legally-mandated purchasing cycle that makes the waterfall desirable and more Agile methods undesirable.

Thursday, December 1, 2011

Agile "Religion" Issues

See this Limitations of Agile Software Development and this The Agile "Religion" -- What?.  What's important is that the limitations of Agile are not limitations.  They're (mostly) intentional roadblocks to Agile.

Looking for "limitations" in the Agile approach misses the point of Agile in several important ways.
The most important problem with this list of "limitations" is that five of the six issues are simply anti-Agile positions that a company can take.

In addition to being anti-Agile, a company can be anti-Test Driven Development.  They can be Anti-Continuous Integration.  They can be Anti-NoSQL.  There are lots of steps a company can take to subvert any given development practice.  Taking a step against a practice does not reveal a limitation.

"1. A team of stars... it takes more than the average Joe to achieve agility".   This is not a specific step against agility.  I chalk this up to a project manager who really likes autocratic rule.  It's also possible that this is from a project manager that's deeply misanthropic.  Either way, the underlying assumption is that developers are somehow too dumb or disorganized to be trusted.

Agile only requires working toward a common goal.  I can't see how a project manager is an essential feature of working toward a common goal.  A manager may make things more clear or more efficient, but that's all.  Indeed, the "clarity" issue is emphasized in most Agile methods: a "Scrum Master" is part of the team specifically to foster clarity of purpose.

Further, some Agile methods require a Product Owner to clarify the team's direction.

"A team of stars" is emphatically not required.  The experience of folks working in Agile environments confirms this.  Real, working Agile teams really really are average.

"2. Fit with organizational culture".  This has nothing to do with Agile methods.  This is just a sweeping (and true) generalization about organizations.  An organization that refuses autonomy and refuses flexibility can't use Agile methods.  An organization that refuses to create a "Big Design Up Front" can't use a traditional waterfall method and must use Agile methods.

Organizational fit is not a limitation of Agile.  It's just a fact about people.

"3. Small team...Assuming that large projects tend to require large teams, this restriction naturally extends to project size."

The assumption simply contradicts Agile principles.  It's not a "limitation" at all.  Large projects (with large numbers of people) have a number of smaller teams.  I've seen projects with over a dozen parallel Agile teams.  This means that in addition to a dozen daily scrums, there's also a scrum-of-scrums by the scrum masters.

Throwing out the small team isn't a limitation of Agile.  It's a failure to understand Agile.  A project with many small teams works quite well.  It's not "religion".  It's experience.

A single large team has been shown (for the last few decades) to be expensive and risky.

"4. Collocated team...We can easily think of a number of situations where this limitation prevents using agile:"  These are not limitations of Agile, but outright refusals to follow Agile principles.  Specifically:

  • "Office space organized by departments" is not a limitation of Agile.  That's a symptom of an organization that refuses to be Agile.  See #2 above; this indicates a bad fit with the culture.  An organization that doesn't have space organized by department might have trouble executing a traditional waterfall method.
  • "Distributed environment" is not a limitation of Agile.  Phones work.  Skype works.
  • "Subcontracting... We have to acknowledge that there is no substitute for face-to-face".  Actually, subcontracting is irrelevant.  Further, subcontracting is not a synonym for a failure to be collocated.  When subcontractors are located remotely, phones still work.  Skype works better and is cheaper.  
"5. Where’s my methodology?"  This is hard to sort out, since it's full of errors.  Essentially, this appears to be a claim that a well-defined, documented processes is somehow essential to software development.  Experience over the last few decades is quite clear that the written processes and the work actually performed diverge a great deal.  Most of the time, what people do is not documented, and the documented process has no bearing on what people actually do.  A documented process -- in most cases -- appears irrelevant to the work actually done.

Agile is not chaos.  It's a change in the rules to de-emphasize unthinking adherence to a plan and replace this with focus on working software.  Well-organized software analysis, design, code and test still exist even without elaborately documented (and irrelevant) process definitions.

"6. Team ownership vs. individual accountability... how can we implement it since an organization’s performance-reward system assesses individual performance and rewards individuals, not teams...?"  Again, the assumption ("performance-reward system assesses individual performance") is simply a rejection of Agile principles.  It's not a limitation of Agile, it's an intentional step away from an Agile approach.  

If an organization insists on individual performance metrics, see #2.  The culture is simply antithetical to Agile. Agile still works; the organization, however, is taking active steps to subvert it.

Agile isn't a religion.  It doesn't suffer from hidden or ignored "limitations".

"But did we question the assumption that Agile was indeed superior to traditional methodologies?"  

The answer is "yes".  A thousand times yes.  The whole reason for Agile approaches is specifically and entirely because of folks questioning traditional methodologies.  Traditional command-and-control methodologies have a long history of not working out well for software development.  The Agile Manifesto is a result of examining the failures of traditional methods.

A traditional "waterfall" methodology works when there are few unknowns.  Construction projects, for example, rarely have the kinds of unknowns that software development has.  Construction usually involves well-known techniques applied to well-documented plans to produce a well-understood result.  Software development rarely involves so many well-known details.  Software development is 80% design and 20% construction.  And the design part involves 80% learning something new and 20% applying experience.

Agile is not Snake Oil.  It's not something to be taken on faith.  

The Agile community exists for exactly one reason.  Agile methods work.

Agile isn't a money-making product or service offering.  Agile -- itself -- is free.  Some folks try to leverage Agile techniques to sell supporting products or services, but Agile isn't an IBM or Oracle product.  There are no "backers".  There's no trail of money to see who profits from Agility.

Folks have been questioning "traditional" methodologies for years.  Why?  Because "traditional" waterfall methodologies are a crap-shoot.  Sometimes they work and sometimes they don't work.  The essential features of long term success are summarized in the Agile Manifesto.  Well-run projects all seem to have certain common features; the features of well-run projects form the basis for the Agile methods.

Thursday, October 20, 2011

The Agile "Religion" -- What?

Received "it seems that software development has caught the agile religion. Personally, I have an issue w/ being unimodal."

What?

First.  "agile religion".  As in the deprecating statement: Agile is nothing more than a religion?  As in Agile is nothing more than a vague religious practice with no tangible value to an organization?  Interesting, I guess.

I'm assuming that the author did not read the Manifesto for Agile Software Development.  Or--worse-- they read it and find that the four values (Individuals and interactions, Working software, Customer collaboration and Responding to change) are just of no tangible value.

That's alarming.  Really.  The alternative (processes and tools, comprehensive documentation, contract negotiation, and following a plan without regard to changes) seems like it's a recipe for cost, risk, low-value work and a cancelled project.  Indeed, it seems like non-Agile project management is the best way to get to the fabled "Software Crisis" where lots of money gets spent but little of value gets created.

Further, it seems that all modifications of the classic waterfall method (e.g., spiral method as a prime example) specifically create "iterative, incremental" approaches to software development.  That is, everything that's not a strict (brain-dead) waterfall has some elements of Agile.

This causes me to think that Agile isn't a religion.  It causes me to think that Waterfall methods were a religious practice of no tangible value.  All the methodology experiments over the last 15 years have been ways of introducing flexibility (agility, brains) into a foolishly inflexible methodology definition.

Indeed, it appears that the heavy-weigh waterfallish methods are an attempt to replace thinking with process.  And it didn't work.  So, we have to go back to the thinking part.  Only, we call it Agile now.

Religious Wars.

Second.  "agile religion" (again).  As in methodology discussions are just religious wars?  As in methodology discussions are just quibbling over no-value details?  Some folks may get this impression of making a choice between Agile vs. Non-Agile methods.  I think that those folks haven't actually had the opportunity to work from a prioritized backlog and build the most valuable part first.  I think that someone who things Agile is just a religious war hasn't been allowed to fix a broken project plan based on lessons learned during the first release.

Agility.

Third.   "unimodal".  As in being exclusively Agile is bad?  As in sometimes you need to have a rigid, unyielding process that sticks strictly to the schedule irrespective of changes which may occur?  That doesn't seem rational.

Change happens.  Forcing the inevitable changes to conform to some farcical schedule made up by people who didn't have all the details seems silly.  Making contract negotiation the focal point of response to change seems like a waste of effort.  Trying to document everything so completely that all possible changes are already accounted for seems impossible.  And replacing change with a process that regulates change seems -- perhaps -- unhinged.

There were some links and some charts and graphs attached.  I couldn't get past the two sentences above to see if there was, perhaps, something more to it.  All I could do was respond with a request for clarification that didn't involve the trivialization of Agile methods.  It doesn't seem sensible to try and remove the human element from software development.

I'll provide whatever follow-up clarification surfaces on this topic.  It's interesting to see if the "agile religion" was misplaced, or if there are folks who think that responding to the messiness of real software development is a bad idea.

We tried the waterfall method.  And it didn't work very well.  Agile isn't a "religion".  It's a simple acknowledgement that reality is messy.

Tuesday, May 24, 2011

Agility and following a "Strictly Agile" approach

I've seen some discussion on Stack Overflow that is best characterized by the question: "What is Strictly Agile?", or "What's the Official Agile Approach?".

Someone shared this with me recently: "Process kills developer passion".

I have also heard some great complaints about organizations that claim "Agile" and actually do nothing of the kind. In some cases it's not a "crunchy agile shell" around a waterfall process; it's a simple lie. Nothing about the process is Agile except a manager insisting that all the status reporting, planning and unprioritized lists of random requirements are Agile.

Finally, I got this weird suggestion: "consider writing a blog about how to test if you are agile or not". It's weird because testing for Agile is like testing for breathing; it's like testing for flammability.

The Agile Test

Testing if your project is Agile can be done two ways.
  1. Practical. Make a change to the project. Any change. Requirements, architecture, due dates, staff, anything. Does it derail? If so, it wasn't very Agile, was it?
  2. Theoretical. Reread the Agile Manifesto. Make a score card that evaluates the project on each of the eight basic criteria in the Agile manifesto. Convene all the project stakeholders. Conduct careful surveys and have structured walkthroughs to determine the degree of Agility surrounding each person, deliverable, collaborative relationship and issue.
An important point is that Agile is not absolute. Some practices are more Agile than others. There's no "strictly" Agile. There are ways to make a project more Agile; that is, it can effectively cope with change. There are ways to make a project less Agile; that is, change causes problems and can derail the project completely.

The canonical example is a missing, misstated or contradictory requirement that gets uncovered after coding and during user acceptance test. Clearly, that feature has been built and is absolutely wrong. What happens next?

Agile? The product can be released with with the broken feature relegated to the next release. A hack is put in to remove the buttons or menu items or links until they work.

Not Agile? Everyone works around the clock to make that feature work no matter what. Paraphrasing Admiral Farragut: "Technical debt be damned. Development must proceedfull speed ahead." All of this irrespective of the relative value of what's being developed. Schedule comes first; features second.

How Much Process?

The "Process Kills..." blog entry repeats observation that a lot of carefully-defined process isn't really all that helpful. It identifies a cause ("process kills passion") that's can be true, but it's largely irrelevant. Process is—essentially—work that's not focused on delivering anything of real value. Complex processes are "meta" work; it's work focused on IT internals; it's work that creates no value for the users of the software; work that replaces the more valuable elements of the Agile Manifesto.

One can argue that processes, documentation, contracts and plans "assure" success or demonstrate some level of quality. To an extent all the process and meta-work creates trust that—eventually—the resulting software product will solve the original problem.

The mistake is that non-Agile methods use a series of surrogates—processes, documentation, contracts and plans—instead of actual software. The point of Agile methods it to release software early and often and avoid using surrogates.

Key Points of Agile

Here are the key points of the Agile Manifesto.
  • Individuals and interactions over processes and tools. A more Agile project will use the best people and encourage them to talk amongst themselves. A less Agile project will write a lot of things (which folks don't have time or reward for reading.) There will be misunderstandings, leading to large, boring meetings where someone reads powerpoint slides to other folks to try and clear up misunderstandings.
  • Working software over comprehensive documentation. A more Agile project uses frequent release cycles of incremental software. A less Agile project attempts to gather all requirements, do all design and then try to do all the coding even though the requirements have already been found to be less than crystal clear.
  • Customer collaboration over contract negotiation. A more Agile project uses constant contact with customer and product owner to refine and prioritize the requirements. A less Agile project uses a complex change control process to notify everyone of a requirements change, which leads to design and code changes, and has cost and schedule impact that must be carefully planned and documented.
  • Responding to change over following a plan. A more Agile project uses incremental releases, conversation and a modicum of discipline to build things of value. Just because someone thought it should be included in the requirements doesn't mean the feature is really required.
The "Process Kills Passion?" Question

There Process Kills Passion blog lists a bunch of things that—it appears—some folks find burdensome:
  • Doing full TDD, writing your tests before you wrote any implementing code.
  • Requiring some arbitrary percentage of code coverage before check-in.
  • Having full code reviews on all check-ins.
  • Using tools like Coverity to generate code complexity numbers and requiring developers to refactor code that has too high a complexity rating.
  • Generating headlines, stories and tasks.
  • Grooming stories before each sprint.
  • Sitting through planning sessions.
  • Tracking your time to generate burn-down charts for management.
This list has three different collections of practices.
  • Good. TDD, code reviews, generating headlines, stories and tasks, grooming stories before each sprint and doing some planning for each sprint are all simply good ideas. They must be done. "Pure Coding" is not a good way to invest time. Planning and then coding is much smarter, no matter how boring planning appears.
  • Difficult. Test code coverage can be helpful, but can also devolve to empty numerosity. 20% more coverage doesn't not mean 20% fewer bugs. Nor does it mean 20% less chance of uncovering a bug at run time. Code complexity ratings are also fussy because they don't have a direct correlation with much. They must be done and used to prioritize work that will reduce technical debt. But mindless thresholds are for cowards who don't want to mediate deep technical discussions.
  • Silly. Creating burn-down charts for management shouldn't be necessary. Everyone must read and understand the backlog. Everyone should build the summary charts they want from the backlog. The product owner or even the eventual customer should do this on their own. They must be given a profound level of ownership of the features and the process for creating software.
I don't agree that process kills passion. I think there's a fine line between playing with software development and building software of value. I think that valuable software requires some discipline and requires executing a few burdensome tasks (like TDD) that create real value. Assuring 80% or 100% code coverage doesn't always create real value. Spending time keeping the backlog precise and complete is good; spending time making pictures is less good.

Thursday, December 2, 2010

More Open Source and More Agile News

ComputerWorld, November 22, 2010, has this: "Open Source Grows Up". The news of the weird is "It's clear that open-source software has moved beyond the zealotry phase." I wasn't aware this phase existed. I hope to see the project plan with "zealotry" in it.

The real news is "More than two-thirds (69%) of the respondents said they expect to increase their investments in open source." That's cool.

Be sure to read the sidebar "Many Enterprises Aren't Giving Back." There's still a lot of concern over intellectual property. I've seen a lot of corporate software -- it's not that good. Most companies that are wringing their hands over losing control of their trade secrets should really be wringing their hands because their in-house software won't measure up to open-source standards.

I like this other quote: 'Five years ago, the South Carolina government was "considering writing a policy to prohibit or at least 'control' open source".' I like the "Must Control Open Source" feeling that IT leadership has. Without this mysterious "control", the organization could be swamped by software it didn't write. How's that different from being swamped by software products that involve contracts and fees? And requires Patch Tuesday?

Agility

SD Times has two articles on Agile methods. Both on the front page of a print publication. That's how you know the technique has "arrived".

First, there's "VersionOne survey finds agile knowledge and use on the rise". My favorite quote: "Interestingly, management support, the ability to change organizational culture and general resistance to change, remained at the forefronts of participants’ minds when indicating barriers to further agile adoption." I like the management barriers. I like it when management tries to exert more 'control' over a process (like software creation) that's so poorly understood.

Here's the companion piece, "For agile success, leaders must let teams loose". This is all good advice. Particularly, this: '"It’s hard to not command and control, but leadership is not about managing work. It’s about creating a capable organization that can manage work," [Rick Simmons] added.'

If you're micro-managing, you're not building an organization. Excellent advice. However, tell that to the financial control crowd.

Budgets and "Control"

Finally, be sure to read this by Frank Hayes in ComputerWorld: "Big Projects, Done Small". Here are the relevant quotes: "The logical conclusion: We should break up all IT projects into sub-million-dollar pieces." "The political reality: Everybody wants multimillion-dollar behemoths." "...huge projects get big political support."

In short, Agile is the right thing to do until you're trying to get approval. Bottom line: use Agile methods. But for purposes of pandering to executives who want to see large numbers with lots of zeroes, it's often necessary to write giant project "plans" that you don't actually use.

Go ahead, write waterfall plans. Don't feel guilty or conflicted. Some folks won't catch up with Agility because they think "Control" is better. Pander to them. It's okay.

Tuesday, October 19, 2010

Technical Debt

Love this from Gartner. "Gartner Estimates Global 'IT Debt' to Be $500 Billion This Year, with Potential to Grow to $1 Trillion by 2015".

NetworkWorld ran a quicky version of the story. Gartner: Global 'IT debt' hits $500 billion, on the way to $1 trillion.

ComputerWorld -- to be proper journalists -- have to get a balancing quote. Their version of the story is this: Gartner warns of app maintenance 'debt'. The balancing quote is the following:
"There are many good reasons to NOT upgrade/modernize many applications, and I believe Gartner is out of line using words like 'debt' which have guilt associated with them,"
"Guilt"? That's a problem? Why are we pandering to an organization's (i.e., CIO's) emotional response?

I'm not sure that using a word like "debt" is a problem. Indeed, I think they should ramp up the threat level on this and add words like "short-sighted" and "daft" and perhaps even "idiotic".

Anyone who doesn't believe (or doesn't understand) technical debt needs only to review the Y2K plans and budgets. A bad technology decision lead to a mountain of rework. Yes, it was all successful, but it made IT budgeting difficult for years afterwords.

The rest of the organization was grumpy about having their projects were stalled until after Y2K. IT created it's own problems by letting the technology debt accumulate to a level where it was "fix or face an unacceptable risk of not being able to stay in business."

How many other latent Y2K-like problems are companies ignoring?

Thursday, February 4, 2010

ALM Tools

There's a Special Report in the January 15 SDTimes with a headline that bothers me -- a lot. In the print edition, it's called "Can ALM tame the agile beast?". Online it's ALM Tools Evolve in the Face of Agile Processes.

The online title makes a lot more sense than the print title. The print title is very disturbing. "Agile Beast?" Is Agile a bad thing? Is it somehow out of control? It needs to be "tamed"?

The article makes the case -- correctly -- that ALM tools are biased toward waterfall projects with (a) long lead times, (b) a giant drop of deliverables, and (c) a sudden ending. Agile projects often lack these attributes.

The best part of the special report is the acknowledgement that "barriers between developers and QA are disappearing". TDD works to blur the distinction between test and development, which is a very good thing. Without unit tests, how do you know you're finished coding?

How Many Tools Do We Need?

The point in the article was that the ALM vendors have created a collection of tools, each of which seems like a good idea. However, it's too much of the wrong thing for practical, Agile, project management.

The article claims that there were three tools for requirements, tests and defects. I've seen organizations with wishlists that are much bigger than these three. The Wikipedia ALM Article has an insane list of 16 tools (with some overlaps).

Of these, we can summarize them into the following eight categories, based on the kind of information kept. Since the boundaries are blurry, it isn't sensible to break these up by who uses them.
  • Requirements - in user terms; the "what"
  • Modeling and Design - in technical terms; an overview of "how"
  • Project Management (backlog, etc.) - requirements and dates
  • Configuration Management - technology components
  • Build Management - technology components
  • Testing - components, tests (and possibly requirements)
  • Release and Deployment - more components
  • Bug, Issue and Defect Tracking - user terms, requirements, etc.
Agile methods can remove the need for most (but not all) of these categories of tools. If the team is small, and really collaborating with the users, then there isn't the need to capture a mountain of details as well as complex management overviews for slice-and-dice reporting.

YAGNI

Here's a list of tools that shouldn't be necessary -- if you're collaborating.
  • Requirements have an overview in the backlog, on the scrumboard. Details can be captured in text documents written using simple markup like RST or Markdown. You don't need much because this is an ongoing conversation.
  • Modeling and Design is a mixture of UML pictures and narrative text. Again, simpler tools are better for this. Tool integration can be accomplished with a simple web site of entirely static content showing the current state of the architecture and any detail designs need to clarify the architecture. Write in RST, build it with Sphinx.
  • Project Management should be simply the backlog. This is digested into periodic presentations to various folks outside the scrum team. There isn't much that can be automated.
For UML pictures, ARGO UML is very nice. Here's a more complete list of Open Source UML Tools from Wikipedia.

Configuration Management

This is, perhaps, the single most important tool. However, there are two parts to this discipline.
For Revision Control, Subversion works very nicely.

Continuous Integration

The more interesting tools fall under the cover of "Continuous Integration". Mostly, however, this is just automation of some common tasks.
  • Build Management might be interesting for complex, statically compiled applications. Use of a dynamic language (e.g., Python) can prevent this. Build management should be little more than Ant, Maven or SCons.

    Additional tools include the Build Automation list of tools.

  • Testing is part of the daily build as well as each developer's responsibility. It should be part of the nightly build, and is simply a task in the build script.

    Overall integration or acceptance testing, however, might require some additional tools to exercise the application and confirm that some suite of requirements are met. It may be necessary to have a formal match-up between user stories and acceptance tests.

    There's a Wikipedia article with Testing Tools and Automated Testing. Much of this is architecture-specific, and it's difficult to locate a generic recommendation.

  • Release and Deployment can be complex for some architectures. The article on Software Deployment doesn't list any tools. Indeed, it says "Because every software system is unique, the precise processes or procedures within each activity can hardly be defined."

    Something that's important is a naming and packaging standard, similar to that used by RPM's or Python .egg files. It can be applied to Java .EAR/.WAR/.JAR files. Ideally, the installed software sits in a standard directory (under /opt) and a configuration file determines which version is used for production.

    Perhaps most important is the asset tracking, configuration management aspect of this. We need to plan and validate what components are in use in what locations. For this BCFG2 seems to embody a sensible approach.

For most build, test and release automation, SCons is sufficient. It's easily extended and customized to include testing.

More elaborate tools are listed in the Continuous Integration article.

Customer Relationship Management

The final interesting category isn't really technical. It includes tools for Bug, Issue and Defect Tracking. This is about being responsive to customer requests for bug fixes and enhancements.

The Comparison of Issue Tracking Systems article lists a number of products. Bugzilla is typical, and probably does everything one would actually require.

Old and Busted

I've seen organizations actively reject requirements management tools and use unstructured documents because the tool (Requisite Pro) imposed too many constraints on how requirements could be formalized and analyzed.

This was not a problem with tool at all. Rather, the use of a requirements management tool exposes serious requirements analysis and backlog management issues. The tool had to be dropped. The excuse was that it was "cumbersome" and didn't add value.

[This same customer couldn't use Microsoft Project, either, because it "didn't level the resources properly." They consistently overbooked resources and didn't like the fact that this made the schedule slip.]

When asked about requirements tools, I suggest people look at blog entries like this one on Create a Collaborative Workspace or these pictures of a well-used scrumboard.

Too much software can become an impediment. The point of Agile is to collaborate, not use different tools. Software tools can (and do) enforce a style of work that may not be very collaborative.

Bottom Line

Starting from the ALM overview, there are potentially a lot of tools.

Apply Agile methods and prune away some of the tools. You'll still want some design tools to help visualize really complex architectures. Use Argo UML and plain text.

Developers need source code revision control. Use Subversion.

Most everything else will devolve to "Continuous Integration", which is really about Build and Test, possibly Release. SCons covers a lot of bases.

You have some asset management issues (what is running where?) There's a planning side of this as well as an inventory side of confirming the configuration. Use BCFG2.

And you have customer relationship management issues (what would you like to see changed?) Use Bugzilla.

Monday, October 26, 2009

Process Not Working -- Must Have More Process

After all, programmers are all lazy and stupid.

Got his complaint recently.

"Developers on a fairly routine basis check in code into the wrong branch."

Followed by a common form of the lazy and stupid complaint. "Someone should think about which branch is used for what and when." Clearly "someone" means the programmers and "should think about" means are stupid.

This was followed by the "more process will fix this process problem" litany of candidate solutions.

"Does CVS / Subversion have a knob which provides the functionality to
prevent developers from checking code into a branch?"

"Is there a canonical way to organize branches?" Really, this means something like what are the lazy, stupid programmers doing wrong?

Plus there where rhetorical non-questions to emphasize the lazy, stupid root cause. "Why is code merging so hard?" (Stupid.) "If code is properly done and not coupled, merging should be easy?" (Lazy; a better design would prevent this.) "Perhaps the developers don't understand the code and screw up the merge?" (Stupid.) "If the code is not coupled, understanding should be easy?" (Both Lazy and Stupid.)

Root Cause Analysis

The complaint is about process failure. Tools do not cause (or even contribute) to process failure. There are two possible contributions to process failure: the process and the people.

The process could be flawed. There could be no earthly way the programmers can locate the correct branch because (a) it doesn't exist when they need it or (b) no one told them which branch to use.

The people could be flawed. For whatever reason, they refuse to execute the process. Perhaps they know a better way, perhaps they're just being jerks.

Technical means will not solve either root cause problem. It will -- generally -- exacerbate it. If the process is broken, then attempting to create CVS / Subversion "controls" will end in expensive, elaborate failure. Either they can't be made to work, or (eventually) someone will realize that they don't actually solve the problem. On the other hand, if the people are broken, they'll just subvert the controls in more interesting, silly and convoluted ways.

My response -- at the time -- was not "analyze the root causes". When I first got this, I could only stare at it dumbfounded. My answer was "You're right, your developers are lazy and stupid. Good call. Add more process to overcome their laziness and stupidity."

After all, the questioner clearly knows -- for a fact -- that more process helps fix a broken organization. The questioner must be convinced that actually talking to people will never help.
The question was not "what can I do?" The question was "can I control these people through changes to CVS?" There's a clear presumption of "process not working -- must have more process."

The better response from me should have been. "Ask them what the problem is." I'll bet dollars against bent pins that no one tells them which branch to use in time to start work. I'll bet they're left guessing. Also, there's a small chance that these are off-shore developers and communication delays make it difficult to use the correct branch. There may be no work-orders, just informal email "communication" between on-shore and off-shore points-of-contact (and, perhaps, the points-of-contact aren't decision-makers.)

Bottom Line. If people can't make CVS work, someone needs to talk to them to find out why. Someone does not need to invent more process to control them.

Thursday, October 22, 2009

Breaking into Agile

I had a recent conversation with some folks who were desperate to "processize" everything. They were asking about Scrum Master certification and what standards organizations define the "official" Scrum method.

Interestingly, I also saw a cool column in Better Software magazine, called "Scrumdamentalism" on the same basic question.

In my conversation, I referred them to the Agile Manifesto. My first point was that process often gets in the way of actual progress. Too much process focus lifts up "activity" in place of "accomplishment".

My second point, however, was that the Agile Manifesto and the Scrum method are responses to a larger problem. Looking for a process isn't an appropriate response to the problem.

The One True Scrum Quest

Claiming that there's one true Scrum method and everything else is "not scrum" is an easy mental habit. The question gets asked on Stack Overflow all the time. The questions are usually one of two kinds.
  • What's the "official" or "best practice" Scrum method and how do I define a process that rigidly enforces this for my entire team of 20?
  • We are doing our design/code/test/integration/release in a way that diverges from the "official" form in the Ken Schwaber and Mike Beedle book. Or it diverges from the Eclipse version. Or it diverges from the Control Chaos overview. Or the Mountain Goat version. Or the C2 Wiki version. Or this version. Is it okay to diverge from the "standard"?
Sigh. The point of Agile is that we should value "Individuals and interactions over processes and tools". The quest for "One True Scrum" specifically elevates the process above the people.

In The Real World

The biggest issue is that the Agile Manifesto is really a response to some fundamental truths about software development.

In management fantasy world, a "project" as a fixed, definite, limited, clearly articulated scope. From this fixed scope, we can then document "all" the requirements (business and technical). This requirements document is (a) testable against the scope, (b) necessary for all further work and (c) sufficient for design, code, test and transition to production. That's not all. And -- in order to make a point later on -- I'll continue to enumerate the fantasies. The fantasy continues that someone can create a "high-level design" or "specification" that is (a) testable against the requirements, (b) necessary for all further work and (c) sufficient to code, test and transition to production. We can then throw this specification over the transom into another room where a "coder" will "cut code" that matches the specification. The code production happens at a fixed, knowable rate with only small random variation based on risk of illness. The testing, similarly, can be meticulously scheduled and will happen precisely as planned. Most "real-world" (management fantasy) projects do not leave any time for rework after testing -- because rework won't happen. If it won't happen, why test? Finally, there will be no technology transfer issues because putting a freshly-written program into production is the same as installing a game from a DVD.

Managers like to preface things with "In The Real World". As in "In The Real World we need to know how long it will take you to write this."

The "in the real world" speech always means "In My Management Fantasy Land." The reason it's always a fantastic speech is because software development involves the unknowable. I'm not talking about some variable in a formula with a value that's currently unknown. I'm talking about predicting the unknowable future.

The Agile Response to Reality

In the Real real world, software development is extraordinarily hard.

Consider this: the computer clock runs in 100-nanosecond increments (1.0E-7). We expect an application to run 24x7x0.999 = 6.04E5 seconds. That's from 100-nano to half-million: about 12 orders of magnitude to keep in one's head.

Consider this: storage in a largish application may span almost a terabyte, (1.0E12). From bytes to terabytes: about 12 orders of magnitude to keep in one's head.

Consider this: a web application written in a powerful framework (Django) requires one to know the following languages and frameworks. Shell script, Apache Config, Python, Django Templates, SQL, HTML, CSS, Javascript, HTTP (the protocol is it's own language), plus the terminology of the problem domain. That's 9 distinct languages. We also have the OS, TCP/IP Apache, mod_wsgi, Django, Python, browser and our application as distinct frameworks. That's 8 distinct framework API's to keep in one's head.

Consider this: the users can't easily articulate their problem. The business analyst is trying to capture enough information to characterize the problem. The users, the analyst, the project manager (and others outside the team) all have recommendations for a solution, polluting the problem description with "solution speak" that's only adds confusion.

In the Management Fantasy "Real World", this is all knowable and simple. In the Real Real World, this is rather hard.

Adapting to Reality

Once we've recognized that software development is hard, we have several responses.
  1. Deny. Claim that software developers are either lazy or stupid (or both). Give them pep-talks that begin "in the real world" and hope that they cough up the required estimates because they're motivated by being told that software development "in the real world" isn't all that hard.
  2. Processize(tm). Claim that software development is a process that can be specified to a level where even lazy, stupid programmers can step through the process and create consistent results.
  3. Adapt. Adapting to the complexity of software development requires asking, "what -- if anything -- expedites software development?"
What Do We Need to Succeed?

There are essentially two domains of knowledge required to create software: the problem domain and the solution domain.
  • Problem Domain. This is the "business rules", the "scope", the "requirements", the "purpose", etc. We have the features and functions. What the software does. The value it creates. The "what", "who", "where", "when" and "why".
  • Solution Domain. This is the technology that makes it go. The time and space dimensions (all 12 orders of magnitude in each dimension), all the languages and all the frameworks. The "how".
The issue is this:

We don't start out with complete knowledge of problem and solution.

At the start of the project -- when we're asked to predict the future -- we can never know the whole problem, nor can we ever know the whole solution we're about to try and build.

What we need is this:

Put Problem Domain and Solution Domain knowledge into one person's head.

The question then becomes "Who's head?"

We have two choices:
  • Non-Programmers. We can try to teach the various non-programmers all the solution domain stuff. We can make the project manager, business analyst, end-users, executive sponsor -- everyone -- into programmers so that they have problem domain and solution domain knowledge.
  • Programmers. We can try to impart the problem domain knowledge on the programmers. If we're seriously going to do this, we need to remove the space between programmer and problem.
That's the core of the Agile Response: Close the gap between Problem Domain and Solution Domain by letting programmers understand the problem.

The Bowl of Bananas Solution(tm)

"But wait", managers like to say, "in the real world, we can't just let you play around until you claim you're done. We have to monitor your activity to make sure that you're making 'progress' toward a 'solution'."

In the Real real world, you can't define the "problem", much less test whether anything is -- or is not -- a solution. I could hand most managers a bowl of bananas and they would not be able to point to any test procedure that would determine if the bowl of bananas solves or fails to solve the user's problems.

Most project scope documents, requirements documents, specifications, designs, etc., require extensive tacit problem domain knowledge to interpret them. Given a bowl of bananas, the best that we can do is say "we still have the problem, so this isn't a solution." Our scope statements and requirements and test procedures all make so many assumptions about the problem and the solution that we can't even figure out how evaluate an out-of-the-box response -- like a bowl of bananas.

In the Real real world, management in organization A demands that information be kept in a one database. Management organization B has a separate database for reasons mired in historical animosity and territorial scent-marking. Management in yet another organization wants them "unified" or "reconciled" and demands that someone manually put the data into spreadsheets. This morphs into requirements for a new application "system" to unify this data, making the results look like poorly-design spreadsheets. This morphs into a multi-year project to create a "framework" for data integration that maintains the poorly-designed spreadsheet as part of the "solution".

A quick SQL script to move data from A to B (or B to A) is the bowl-0f-bananas solution. It cannot be evaluated (or even considered) because it isn't a framework, system or application as specified in the scope document for the data integration framework.

This is the problem domain knowledge issue. It's so hard to define the problem, that we can't trust the executive sponsor, the program office, the project managers, the business analysts or anyone to characterize the problem for the developers.

The problem domain knowledge is so important that we need to allow programmers to interact with users so that both the problem and the solution wind up in the programmer's head.

Friday, October 2, 2009

Agile Methods and "Total Cost"

Many folks ask about Agile project planning and total cost. As our internal project managers wrestle with this, there are a lot of questions.

Mostly these questions are rejections of incremental delivery ("All or Nothing") or rejections of flexibility ("Total Total Cost"). We'll look at these rejections in detail.

Traditional ("waterfall") project planning creates a master plan, with all skills, all tasks, all effort, and all costs. It was easy to simply add it up to a total cost.

Software development, unlike -- for example -- carpentry, has serious unknowns. Indeed software development has so many unknowns that it's not possible to compare software project management with the construction trades.

A carpenter has a task ("frame up these rooms") that has an absolute boundary with no unknown deliverables. No one says things like "we need to separate the functions of these users from those users." They say "build a wall, surface dry-wall, tape, paint, add molding." The carpenter measures, and knows precisely the materials required.

The carpenter rarely has new technology. The pace of change is slow. A carpenter may switch from hand-held nails to a nail gun. It's still nails. The carpenter may switch from wooden 2x4's to metal supports. It's still vertical members and nails. The carpenter may switch brands of wall-board. It's still wall-board.

The consequence of this is that -- for software projects -- Total Cost Is Hard To Predict.

Hack-Arounds

Total cost is hard to predict, but we try to do it anyway. What we do is add "risk factors" to inflate our estimate. We add risk factors for the scope of delivery. We add risk factors for our ability to deliver.

We can organize these risk factors into several subtle buckets. The COCOMO model breaks scope down into three Product Attributes and four Hardware Attributes. It breaks delivery down into five Personnel Attributes and three Project Attributes.

This is a hack-around because we simply cannot ever know the final scope, nor can we ever know our ability to deliver. We can't know our ability to deliver because the team is constantly changing. We should not cope with this expected constant state of flux by writing an elaborate plan and then reporting our failure to meet that plan. That's stupid.

Worse still, we can't know the scope because it's usually a fabric of lies.

Scope Issue 1: "Required"

Customers claim that X, Y and Z are "required". Often, they have no idea what "required" even means. I spent a fruitless hour with a customer that had a 24×7 requirement. I said, "you haven't purchased hardware that will give you 24×7, so we're submitting this change order to remove it from the requirements."

They said, "It's more of a goal. We don't want to remove it."

I said, "It cannot be achieved. You will not pay us because we will fail. Can we remove it and rewrite it as a 'goal'?"

They said, "No need to remove it: we wouldn't failure to meet that requirement as a 'failure'."

"Okay," I said, "what's the minimum you'll put up with before suing us for failing?"

They couldn't answer that. They had no "required" up-time and could not determine what was "required". They had a goal, but no minimum that would trigger labeling the project a failure.

Of course, the project failed. But not because of up-time. There were dozens of these kinds of poorly-worded requirements that weren't really required.

Scope Issues 2: "The Game"

I worked with some users who were adept at gaming IT. They knew that IT was utterly incapable of delivering everything in the requirements document. They knew this and planned on it.

Also, the users knew that a simple solution would not "add enough value"; a simple solution would get rejected by the governance committee. They knew this and planned on it also.

The users would write amazing, fabulous, wondrous requirements, knowing that some of them were sacrificial. The extra requirements were there to (1) force IT to commit serious resources to the project and (2) convince governance that the software "added enough value".

IT spent (wasted?) hours planning, architecting, designing, estimating and tracking progress against all of the requirements. Then, when we got to acceptance testing, there were numerous "requirements" that were not required, nor even desired. They were padding.

What To Do?

Okay. Scope and delivery are unknowable. Fine. In spite of this, what do we do to provide a reasonable estimate of development effort?
  1. Gather the "requirements" or "desires" or "wishes" or "epics" or "stories" or whatever you've got that provides some scope definition. This is the "analysis" or "elaboration" phase. Define "what", but not "how". Clearly define the business problem to be solved. Avoid solution-speak like "database", "application server", and the like.
  2. Decompose. Define a backlog of sprints based on what you know. If necessary, dig into some analysis details to provide more information on the sprints. Jiggle the sprints around to get a consistent size and effort.
  3. Prioritize based on your best understanding. Define some rational ordering to the sprints and releases. Provide some effort estimate for the first few releases. This estimate is simply the sum of the sprint costs. The sprints should be all about the same effort and about the same cost. About. Not exactly. Fine tune as necessary.
  4. Prioritize again with the users. Note that the sprint costs and the sprints required to release are all in their face. They can adjust the order only. Cost is not negotiable. It's largely fixed.

Rejection 1: All Or Nothing

One weird discussion point is the following: "Until release X, this is all useless. You may as well not do release 1 to X-1, those individual steps are of no value."

This is not true, but it's a way some folks try to reject the idea of incremental releases.

You have two possible responses.
  • "Okay." In this case, you still create the releases, you just don't deliver them. We watched two members of the customer's management team argue about the all-or-nothing issue. One bone-head kept repeating that it was all-or-nothing. Everyone else claimed that Release 1 and 2 were really helpful, it was release 3 to X-1 that were not so useful.
  • "What not?" In this case, you suspect that the priorities are totally wrong and -- for some reason -- the customer is unwilling to put them in the correct order.
Everything can be prioritized. Something will be delivered first. At the very least, you can play this trump card. "We need to do incremental releases to resolve any potential problems with delivery and turn-over."

Rejection 2: Total Total Cost

The most frustrating conversations surround the "total cost" issue.

The trick to this is the prioritization conversation you had with your users and buyers. Step 4, above.

You gave them the Release - Sprint - Cost breakdown.

You walked through it to put the releases and sprints into the correct order.

What you have to do is add another column to the spread-sheet: "Running Cost". The running cost column is the sum of the sprint costs. Each running cost number is a candidate total cost. It's just that simple.

It takes several tries to get everyone's head wrapped around the concept.

Customer Control

You know the concept has started to sink in when the customer finally agrees that they can pull the plug on the project after any sprint. They grudgingly admit that perhaps they control the costs.

You know they really get it when they finally say something like this.

"We can stop at any time? Any time? In that case, the priority is all wrong. You need to do X first. If we were -- hypothetically -- going to cancel the project, X would create the most value. Then, after that, you have to do Z, not Y. If we cancel after X and Z, we've solved most of the real problems."

When they start to go though hypothetical project cancelation scenarios with you, then they get the way that they control the total cost.

This tends to avoid the tedious of negotiations where the customer then changes the requirements to meet their budget. Nothing is more awful than a customer who has solicited bids via a Request for Proposal (RFP) process. They liked our bid, but realized that they'd asked for too much, and want to reduce the scope, but don't have priorities or cost-per-release information.

If you do the priorities interactively -- with the customer -- there's no "negotiation". It's just decision-making on their part.

Thursday, October 1, 2009

Agile Project Management

Got this question recently.
"Any suggestions on PM tools that meet the following considerations

1) Planning

2) Estimating

3) Tracking (allowing both PM input and developer input)

4) Reporting

5) Support both Agile and Waterfall projects

6) Releases

7) Bug fixes (probably just another type of backlog)"



Agile PM requires far less planning than you're used to.

1. A "backlog" which is best done on a spreadsheet.

2. Daily standup meetings which last no more than 15 minutes at the absolute longest.

And that's about it.

Let's look at these expectations in some detail. This is important because Agile PM is a wrenching change from waterfall PM.

Planning

There are two levels of detail in planning. The top level is the overall backlog. This is based on the "complete requirements" (hahaha, as if such a thing exists). You have an initial planning effort to decompose the "requirements" into a workable sequence of deliverables and sprints to build those deliverables. Don't over-plan -- things will change. Don't invest 120 man-hours of effort into a plan that the customer will invalidated with their first change request. Just decompose into something workable. Spend only a few days on this.

The most important thing is to prioritize. The backlog must always be kept in priority order. The most important things to do next are at the top of the backlog. At the end of every sprint, you review the priorities and change them so that the next thing you do is the absolutely most valuable thing you can do. At any time, you can stop work, and you have done something of significant value. At any time, you can review the next few sprints and describe precisely how valuable those sprints will be.

The micro level of detail is the next few deliverables. No more than four to six. Don't over-plan. Review the deliverables in the backlog, correcting, expanding, combining and refining as necessary to create something that will be of value. List the sprints to build those deliverables. Try to keep each sprint in the four week range. This is really hard to do at first, but after a while you develop a rhythm based on features to be built and skills of the team. You don't know enough going in, so don't over-plan. After the first few sprints you'll learn a lot about the business problem, the technology and the team.

Estimating

Rule 1: don't. Rule 2: the estimate is merely the burn rate (cost per sprint) times the number of sprints. Each sprint involves the whole team building something that *could* be put into production. A team of 5 with 4 week sprints is a cost of 5*40*4 (800 man-hours).

Each sprint, therefore, has a cost of 800 man-hours. Period. The overall project has S sprints. If the project runs more than a year, stop. Stop. The first year is all you can rationally estimate this way. Future years are just random numbers. 5*40*50 = 10,000 man-hours.

Details don't matter because each customer change will invalidate all of your carefully planned schedules. Just use sprints and simple multiplies. It's *more* accurate since it reflects the actual level of unknowns.

What about "total cost"? First, define "total". When the project starts is the "complete requirements" (hahahaha, as if such a thing actually exists). Then, with each customer change, this changes. Further, half the requirements are merely "nice-to-haves". Since they're merely nice, they're low priority -- at the bottom of the backlog.

Since each sprint creates something deliverable, you can draw a line under any sprint, call it "done" and call that the "total cost". Any sprint. Any. There are as many different total costs as there are sprints, and all of them are right.

Tracking

I don't know what this is. I assume it's "tracking progress of tasks against a plan". Since the tasks are not planned at a low level of detail, there's nothing to "track".

You have a daily stand-up. People commit to do something that day. The next day you find out if they finished or didn't finish. This isn't a "tool thing". It's a conversation. Done in under 15 minutes.

Two things can happen during this brief conversation.

- Things are progressing as hoped. The sprint will include all hoped-for features.

- Things are not progressing as hoped. The sprint may not include some feature, or will include an incomplete implementation. The sprint will never have bugs -- quality is not sacrificial. Features are sacrificial.

There's no management intervention possible. The sprint will have what it will have. Nothing can change that. More people won't help. Technology changes won't help. Design changes won't help. You're mid-sprint. You can only finish the sprint.

AFTER the sprint is over, and you've updated the backlog and fixed the priorities, you might want to consider design changes or technology changes.

Reporting

What? To Whom? Each sprint is a deliverable. The report is "Done".

The backlog is a shared document that the users "own" and you use to assure that the next sprint is the next most important thing to do.

Support both Agile and Waterfall projects

Not possible. Incompatible at a fundamental level. You can't do both with one tool because you don't use tools for Agile projects. You just use spreadsheets.

Releases

Some sprints are release sprints. They're no different (from a management perspective) than development sprints. This is just CM.

Bug fixes

Probably just another type of backlog. Correct.